Project Background

Distribution mainline pipes are the backbone of LADWP’s water distribution system. There are approximately 6,780 miles of mainline pipe and 27 percent are over 80 years old. With a focus on infrastructure improvement programs, LADWP will continue to provide customers with a reliable source of water by upgrading major system components that are old, or located in seismic areas.

The existing 6-inch cast-iron mainline is over 60-years old and will be replaced with a more substantial 12-inch, earthquake resilient ductile iron pipe on a one-mile stretch of De Soto Avenue from Nordhoff to Bryant. The project also includes portions of Bryant and Osborne as shown on the map.

Project Benefits

  • Replace Aging Infrastructure
  • Enhance Fire Protection
  • Improve water system reliability and flexibility
  • Increase resiliency to seismic activity and water system durability

Construction Schedule

June 2019 – Summer 2021      
The project consists of five work phases as follows:

Phase Location Date and Status
Phase 1 De Soto Ave. from Nordhoff St. to just south of Osborne

Complete

Phase 2 Osborne St. from De Soto Ave. to Independence Ave

Complete

Phase 3 De Soto Ave. from just south of Orborne St. to Parthenia St.

Complete

Phase 4 De Soto Ave. from Parthenia St. to Bryant St.

2021

Phase 5 Bryant St. from De Soto Ave. to end of cul-de-sac.

2021

LADWP crews will use a rolling construction method which limits construction areas to a single, 1,000-foot section to minimize the traffic impact on the community.      
       
Construction crew work hours will be scheduled to coincide with the zoning in the area.

  • Construction near businesses will be performed at night to minimize traffic impacts and economic losses in the community.
  • Construction near residential zones will be performed during the day.

Nighttime operation hours (Business section)      
Nordhoff Street to just south of Osborne and including Osborne Street.      
9:00 p.m. to 5 a.m. Monday – Friday

Daytime operation hours (Residential section)      
9:00 a.m. to 3:30 p.m., Monday – Friday

Occasional Saturday work may occur between 8:00 a.m. and 6:00 p.m.

At the end of each work shift, trenches will be covered with steel plates to maintain driveway access until the next work shift begins.

Traffic Information

In active construction areas, there will always be at least one northbound and one southbound lane open at all times, except when nighttime work is conducted in the intersection at Nordhoff and De Soto. For the safety of the crew and the public, all southbound lanes will be closed while work is done in this intersection.

Temporary tow-away/no-parking signs will be posted as needed. Local and driveway access will be provided.

Contact Us

W. Valley District Superintendent      
John Cox      
818-775-5422      
[email protected]

Asst. Superintendent      
George Larochelle      
818-775-5451      
[email protected]

W. Valley District Engineer      
Rafael Viramontes      
213-367-3320      
[email protected]

W. Valley Field District Engineer      
William Jones      
818-775-5490      
[email protected]

Community Liaison      
Christina Holland      
213-367-1076      
[email protected]