To support growing electricity demand in the Brentwood community, LADWP will be installing three pole-top transformer racks in the neighborhood. These upgrades will help reduce strain on the distribution system and improve operational flexibility for the neighborhoods supplied by Distributing Station 66 (DS-66).

By increasing capacity and improving reliability, these installations are expected to minimize the frequency and duration of service interruptions – especially during periods of high demand.

Construction Information

Once installed, the pole-top transformer racks make minimal operational sound and will have minimal impact on the surrounding community. The equipment is designed and installed in accordance with strict safety standards and is mounted on non-combustible metal poles, providing an added safety benefit. During construction, nearby residents may experience typical temporary construction-related effects such as noise, traffic, and dust in the immediate construction area.

Project Location

The pole-top transformers will be located on San Vicente Blvd. and S. Gretna Green Way, Gorham Ave. and S. Barrington Ave., and Sunset Blvd. between San Remo Dr. and Allenford Ave. The first site scheduled for construction will be located on San Vicente Blvd. and S. Gretna Green Way.

Brentwood Pole-Top Transformer Racks Project Map - San Vicente Bl, Barrington Ave, and Grenta Green Way
Brentwood Pole-Top Transformer Racks Project Map - Sunset Blvd and San Remo Dr

 

Project Schedule

Construction is anticipated to occur from August 2026 through January 2027, with commissioning expected between January and April 2027. Construction will take place Monday through Friday from 8:00 a.m. to 5:00 p.m., with occasional work on Saturdays.

Phase 1 Pole Installation

Pole Top 199 (near DS66) - Early August 2026

Pole Top - 203 (on Sunset, near Allenford) - August 2026, pending equipment availability

Pole Top 202 (on Gorham Ave and S Barrington Ave, behind Starbucks) - Early fall, pending redesign

Phase 2 Circuit & Line Work

Schedule TBD

 