Project Background

The Little Lake Aqueduct Crossover Project involves the design and construction of a crossover trunk line, connecting the First Los Angeles Aqueduct to the Second Los Angeles Aqueduct. The project site is located approximately 10.6 miles south of the Haiwee Power Plant, near Olancha, California, within existing aqueduct rights-of-way. This work will not impact public access to any recreation areas.

Scope of Work

The crossover trunk line will consist of approximately 180 feet of 60-inch diameter welded steel pipe, installed at depths ranging from about 2.5 feet to 10 feet below ground. The crossover will enable the Haiwee Power Plant to continue generating hydroelectric power while the First Los Angeles Aqueduct is out of service for inspection or maintenance.

Little Lake Aqueduct Crossover Project Project Map

Figure I: Site map of location and alignment of the proposed Little Lake Aqueduct Crossover

 

Little Lake Aqueduct Crossover Project Key Map

Figure II: Regional map of Little Lake Aqueduct Crossover relative to California’s Eastern Sierra

Project Schedule

The project is currently in the design phase, with final design completion anticipated in April 2027. The LADWP Board of Commissioners approved a Mitigated Negative Declaration (MND) in accordance with the California Environmental Quality Act (CEQA) for the Little Lake Aqueduct Crossover Project on May 14, 2024. Construction is estimated to begin Winter 2028.

Contact Information

Project Manager:
Kristina Billedo
213-367-9028
Kristina.Billedo@ladwp.com

Assistant Project Manager:
Megan Oliveros
213-367-1192
Megan.Oliveros@ladwp.com

Public Affairs:
Lesly Figueroa
213-982-4076
Lesly.Figueroa@ladwp.com