Massachusetts Ave and Glendon Ave Project Map

Background

Distribution mainline pipes are the backbone of LADWP’s water distribution system. There are approximately 6,794 miles of mainline pipe, of which about 30 percent are over 80 years old. With a focus on infrastructure improvement programs, LADWP will continue to provide customers with a reliable source of water by upgrading major system components that are old, or located in seismic areas.

The Massachusetts Ave and Glendon Ave Project is an important part of LADWP’s plan to accelerate the pace of replacing aging infrastructure. It conforms to LADWP’s Water Infrastructure Plan to promote long-term efficient operation and lower the risk of disruptions due to failure. Customers will benefit from the new mainline pipe with improved water system reliability and flexibility.

Project Description

LADWP crews will replace just over 5,000-ft of existing 4” and 6” cast-iron mainline pipe from the 1920s with new 6” and 8” ductile-iron pipe. The affected streets are Glendon Ave, Malcolm Ave, Holman Ave, and Massachusetts Ave. Impacts to Westwood Blvd and Santa Monica Blvd are not expected at this time. 

A second phase of this project is expected in the future to see the replacement of the water lines on Ohio Ave (Westwood Blvd to Thayer Ave) and Selby Ave (Ohio Ave to Santa Monica Blvd).

Construction Information

Work will be done in block sections to minimize the traffic impact on the community. No traffic impacts have been identified to Westwood Blvd and Santa Monica Blvd, but local streets will have traffic control measures. While construction work is ongoing, only local traffic will be allowed through the work zone. Signs will be posted in advance and flaggers will be present as necessary.

At the end of each work shift, trenches will be covered with steel plates for through traffic and driveway access until the next work shift begins. Crews will work with the community to ensure property access at all times.

Work hours are 9 a.m. to 3:30 p.m., Monday through Friday. Occasional Saturday work may be necessary, 8 a.m. to 6 p.m.

LADWP will provide a 48-hour advance notice when temporary service interruptions are needed to make water mainline connections. 

Other than the connection work, service interruptions throughout the project are expected to be minimal.

Traffic Information

In active construction areas, traffic in each direction will be facilitated. Temporary tow-away/no-parking signs will be posted as needed.

Project Schedule

September 2026 – July 2027

Contact Us

Superintendent
George Larochelle
(213) 276-2187
George.Larochelle@LADWP.com


Assistant Superintendent
Oscar Barragan
(818) 775-5451
Oscar.Barragan@LADWP.com


Community Affairs
Janine Hou
(213) 367-5068
Janine.Hou@LADWP.com