Fly over view of Haynes Generating Station Unit 8 Recycled Water Cooling System Retrofit

Program Background

LADWP is implementing the Haynes Generating Station Unit 8 Recycled Water Cooling System Retrofit Project at Haynes Generating Station located in the City of Long Beach. This project eliminates the use of ocean water cooling (Once-Through-Cooling / OTC) for Unit 8 by constructing a new, wet cooling tower system supplied by recycled water.

Key Project Objectives

  • Eliminate Ocean Water Intake: Phase out ocean water OTC to protect local marine ecosystems in coastal habitats.
  • Utilize Recycled Water Resources: Transition to high-quality recycled water (sourced via regional water reclamation infrastructure, such as the Long Beach Water Reclamation Plant).
  • Comply with Federal and State Regulation: Fulfill the State Water Resources Control Board’s Once-Through Cooling Policy and federal Clean Water Act regulations.
  • Maintain Power System Reliability: Retain Unit 8 as a flexible, dependable generating resource to support grid stability and integrate renewable energy into Los Angeles’s power supply.

Core Infrastructure Changes

  • Cooling System Retrofit: Construction of wet-cooling tower system and associated water circulation piping.
  • Water Supply Integration: Connection to recycled water supply pipelines from local water reclamation facilities.
  • Decommissioning OTC Facilities: Full removal/isolation of Unit 8 from the ocean water intake channel and discharge systems.

Environmental & Community Benefits

  • Marine Life Protection: Completely eliminates marine organism impingement and entrainment associated with ocean water intake for Unit 8.
  • Water Sustainability: Replaces ocean water with recycled water as the cooling medium, maximizing local recycled water utilization and sustainability. In addition, this project effectively reduces overall cooling water utilization for Haynes Unit 8 by 98%.
  • Grid Resilience: Modernizes critical power infrastructure, facilitating the transition toward 100% clean energy while providing peak reliability, efficiency, and resiliency through the transition period.
  • Clean Water Compliance: Aligns operations with federal, state, and local environmental regulations.

Project Status & Milestones

  • CEQA & Environmental Review: Mitigated Negative Declaration (MND) has been completed for the project implementation and the determination was made that the project does not have significant negative environmental impact.
  • Engineering and Construction: Engineering design and equipment procurement is projected from 2027 through 2028. The construction is projected to commence in early 2028, with project completion in May 2030.

Construction Schedule

Project Start Date: January 2028
Estimated Completion Date: May 2030
Work Hours:

  • Monday - Friday 7:00 AM - 5:00 PM
  • Saturday 9:00 AM – 5:00 PM

Contacts

John Levy, Generation Capital Projects | Jonathan.Levy@ladwp.com
Deborah Hong, Community Relations | Deborah.Hong@ladwp.com