Environmental documents may be needed for various LADWP projects to assess environmental impacts. These documents need to be prepared in compliance with the California Environmental Quality Act (CEQA) and/or the National Environmental Policy Act (NEPA). The preparation of environmental documents involves public disclosure to regulatory agencies and the general public to review the data, analysis, and conclusions reached in the environmental documents. Below is a list of archived projects, including project name, notice type, start of public review, and end of public review. Included is also the hearing date of when the Board of Water and Power Commissioners adopted/certified the environmental document and approved the project (CEQA). Click on each Project Name to view more information. Note: All the following information in in English>

Key:
EA Environmental Assessment (NEPA) MND Mitigated Negative Declaration (CEQA)
EIR Environmental Impact Report (CEQA) ND Negative Declaration (CEQA)
DEIR Draft EIR (CEQA) NOD Notice of Determination (CEQA)
FEIR Final EIR (CEQA) NOI Notice of Intent to Prepare an EIS (CEQA)
EIS Environmental Impact Statement (NEPA) NOP Notice of Preparation of an EIR (CEQA)
IS Initial Study (CEQA) TBD To Be Determined

R

Redmont Pump Station and Tank Project

Notice Type NOP DEIR FEIR
Start of Public Review 03/17/16 07/21/16  
End of Public Review 04/16/16 09/22/16  
LADWP Board Hearing Date N/A N/A 11/15/16

PUBLIC MEETING: A public meeting was held on Thursday, August 11, 2016 at 6:00 p.m., 7747 Foothill Boulevard, Tujunga, CA 91042.

 

Redmont Pump Station Replacement Project

Notice Type IS/MND
Start of Public Review 01/15/08
End of Public Review 02/13/08
LADWP Board Hearing Date 07/02/08

 

Replacement of Well 076 in the Bairs-Georges Wellfield

Notice Type IS/MND
Start of Public Review 08/08/11
End of Public Review 09/07/11
LADWP Board Hearing Date 10/04/11

 

Replacement of Well W390 in the Lone Pine Wellfield

Notice Type IS/MND
Start of Public Review 08/08/11
End of Public Review 09/07/11
LADWP Board Hearing Date 10/04/11

 

Reseda Boulevard Pipeline Project

Notice Type IS/MND
Start of Public Review 02/13/14
End of Public Review 03/14/14
LADWP Board Hearing Date 03/06/14

 

River Supply Conduit Improvement – Lower Reach

Notice Type FEIR DEIR NOP/IS
Start of Public Review   05/06/05 08/25/04
End of Public Review   06/20/05 09/23/04
LADWP Board Hearing Date 02/21/06    

 

River Supply Conduit Improvement – Upper Reach

Notice Type FEIR DEIR NOP/IS
Start of Public Review 03/31/08 01/25/07  
End of Public Review 05/15/08 02/26/07  
LADWP Board Hearing Date 09/16/08    

 

Rosamond Switching Station Project

Notice Type NOI/MND
Start of Public Review 04/23/20
End of Public Review 05/25/20
LADWP Board Hearing Date 08/11/20

 

Roscoe Trunk Line Replacement Project

Notice Type NOI/MND
Start of Public Review 03/24/22
End of Public Review 04/22/22
LADWP Board Hearing Date 07/12/22

 

S

San Fernando Basin Groundwater Injection Well Pilot Study

Notice Type NOE
Start of Public Review 04/19/24
End of Public Review 05/24/24
LADWP Board Hearing Date N/A

 

San Fernando Valley Water Recycling Project

Notice Type IS/MND
Start of Public Review 11/16/12
End of Public Review 12/17/12
LADWP Board Hearing Date 11/07/13

 

Santa Ynez Water Quality Improvement Project

Notice Type MND
Start of Public Review 10/30/03
End of Public Review 12/01/03
LADWP Board Hearing Date 07/20/04

 

Scattergood Generating Station Unit 3 Repowering Project

Notice Type NOP/IS NOA/DEIR
Start of Public Review 01/27/11 05/17/12
End of Public Review 02/25/11 07/02/12
LADWP Board Hearing Date   09/18/12

 

 

Scattergood-Olympic Transmission Line

Notice Type NOP NOA/DEIR
Start of Public Review 10/12/10 03/22/12
End of Public Review 11/12/10 05/07/12
LADWP Board Hearing Date   07/17/12

 

 

Sepulveda Basin Water Recycling Project

Notice Type MND
Start of Public Review 11/20/03
End of Public Review 12/19/03
LADWP Board Hearing Date 03/02/04

 

Silver Lake and Ivanhoe Reservoirs Aeration and Recirculation Project

Notice Type NOI/MND
Start of Public Review 05/07/20
End of Public Review 06/05/20
LADWP Board Hearing Date 08/25/20

 

Silver Lake Reservoir Complex Storage Replacement Project

Notice Type FEIR DEIR NOP/IS
Start of Public Review   08/04/05 08/25/03
End of Public Review   09/19/05 09/24/03
LADWP Board Hearing Date 05/16/06    

 

Silver Lake Reservoir Complex Storage Replacement Project

Notice Type FEIR DEIR NOP/IS
Start of Public Review   08/04/05 08/25/03
End of Public Review   09/19/05 09/24/03
LADWP Board Hearing Date 05/16/06    

 

Site Wide Chloramination Trailer Program

Notice Type NOE
Start of Public Review 06/14/22
End of Public Review 07/14/22
LADWP Board Hearing Date N/A

 

 

St. Andrews Place Demolition Project

Notice Type NOI/MND
Start of Public Review 11/16/20
End of Public Review 12/18/20
LADWP Board Hearing Date 04/13/21

 

 

Stormwater Capture Parks Program

Notice Type NOI/MND
Start of Public Review 01/07/21
End of Public Review 02/08/21
LADWP Board Hearing Date 09/14/21

 

Sylmar Ground Return Replacement Project

Notice Type IS/NOP DEIR Recirculated DEIR
Start of Public Review 09/24/10 05/15/14 03/10/16
End of Public Review 10/25/10 09/02/14 04/25/16
LADWP Board Hearing Date TBD TBD 08/02/16

 

The documents below are for the first (2014) release of the DEIR and are here for reference only.

Draft Environmental Impact Report Volume 1:

Draft Environmental Impact Report Volume II:


 

T

Taylor Yard Water Recycling Project

Notice Type IS/MND
Start of Public Review 02/23/07
End of Public Review 03/26/07
LADWP Board Hearing Date 07/17/07

 

Terminal Hill Tunnel and Shaft Project

Notice Type IS/MND
Start of Public Review 09/11/08
End of Public Review 10/10/08
LADWP Board Hearing Date 01/16/09

 

Toluca-Hollywood Line 1 Upgrade Project

Notice Type NOE
Start of Public Review 12/15/22
End of Public Review 03/10/23
LADWP Board Hearing Date 07/11/23

 

Topham Trunk Line Replacement Project

Notice Type NOE
Start of Public Review 06/15/23
End of Public Review 07/15/23
LADWP Board Hearing Date 09/12/23

 

Truesdale Fleet and Maintenance Yard EV Charger Installation Project Exemption

Notice Type NOE
Start of Public Review 08/25/21
End of Public Review 09/24/21
LADWP Board Hearing Date N/A

 

 

Tujunga Spreading Grounds Enhancement Project

Notice Type IS/NOP DEIR
Start of Public Review 02/13/12 08/16/12
End of Public Review 03/15/12 10/31/12
LADWP Board Hearing Date   05/24/13


U

Upper Stone Canyon Reservoir Water Quality Improvement Project

Notice Type NOP/IS DEIR FEIR
Start of Public Review 06/23/08 06/09/11  
End of Public Review 07/22/08 07/25/11  
LADWP Board Hearing Date 02/07/12    

LADWP held a public meeting to solicit comments on the Draft Environmental Impact Report on Tuesday, July 12, 2011 at the American Jewish University. See below to view the presentation from that meeting.


V

Valley Generating Station Demolition Project (Units 1-4 and Associated Structures)

Notice Type NOI/MND
Start of Public Review 01/07/21
End of Public Review 02/08/21
LADWP Board Hearing Date 04/27/21

 

 

Van Norman Bypass Reservoir Solar Project

Notice Type IS/ND
Start of Public Review 07/22/10
End of Public Review 08/10/10
LADWP Board Hearing Date 11/02/10

 

Van Norman Complex Routine Operation and Maintenance Program

Notice Type NOP
Start of Public Review 11/07/19
End of Public Review 12/23/19
LADWP Board Hearing Date 10/12/21

 

 

Victory Pump Station Replacement Project

Notice Type NOI/MND
Start of Public Review 11/30/22
End of Public Review 01/06/23
LADWP Board Hearing Date TBD

 


W

Well V817 Rose Valley Pipeline Installation Project

Notice Type IS/MND
Start of Public Review 08/05/13
End of Public Review 09/04/13
LADWP Board Hearing Date 08/04/15

 

 

West LA District HQ Building

Notice Type IS/MND
Start of Public Review 02/03/05
End of Public Review 03/04/05
LADWP Board Hearing Date 05/03/05

 

 

West Los Angeles District Yard Project

Notice Type NOI/MND
Start of Public Review 06/25/20
End of Public Review 07/25/20
LADWP Board Hearing Date 05/24/22

 

 

Western District Yard Renovation Project

Notice Type IMND
Start of Public Review 06/17/04
End of Public Review 07/19/04
LADWP Board Hearing Date 10/12/04

 

 

Western Trunk Line Project

Notice Type NOI/MND
Start of Public Review 01/23/20
End of Public Review 02/24/20
LADWP Board Hearing Date 07/28/20

 

 

Woodman Avenue Multi-Beneficial Stormwater Capture Pilot Project

Notice Type IS/MND
Start of Public Review 12/13/10
End of Public Review 01/14/11
LADWP Board Hearing Date 02/01/11

 

X

None


Y

None


Z

None