Project Description
The Toluca-Hollywood Line 1 Upgrade Project is part of LADWP's $4.5 billion Power Infrastructure Plan to replace aging infrastructure and improve the reliability of electric service throughout Los Angeles.
The project will replace approximately 1.78 miles of aging underground transmission cables with new, modern cables to improve electric service in the Hollywood and Van Nuys areas.
The existing cables, which have been in service since 1976, will be replaced with new underground transmission cables designed to support current and future electricity needs.
Project Benefits
The Toluca-Hollywood Line 1 Upgrade Project will provide several benefits to the surrounding communities, including:
- Improve the reliability of electric service in the Hollywood and Toluca areas.
- Increase the capacity to deliver electricity to homes and businesses.
- Improve the flexibility and reliability of LADWP's power transmission system.
- Support the integration of additional renewable energy resources.
- Enhance public safety by reducing the risk of failures associated with aging underground cables.
Construction Details
Construction will involve installing new underground conduits, maintenance vaults, and transmission cables between the Hollywood Receiving Station and Nichols Canyon Terminal Tower.
Work will occur in sections along the project route, rather than at one location for the entire construction period. The project will include the removal of existing underground cables and the installation of new infrastructure to support reliable electric service.
Construction activities will include excavation, underground conduit installation, maintenance vault construction, cable installation, and testing.
Construction Schedule
Phase 1: Underground Conduit Construction
November 2026 – May 2027
- Installation of new underground conduits and maintenance vaults between the Hollywood Receiving Station and Hollywood Boulevard.
Phase 2: Cable Installation and Testing
June 2027 – May 2028
- Installation of new underground transmission cables.
- Removal of existing underground infrastructure along Nichols Canyon Road.
- Installation of new underground conduits along Nichols Canyon Road.
- Testing of the new transmission cables.
Anticipated Work Hours:
Monday through Saturday, 7:00 a.m. to 7:00 p.m.
Construction schedules are subject to change based on project conditions and operational needs.
Traffic Plan and Community Impacts
Residents and businesses near the construction areas may experience temporary traffic and parking restrictions while work is underway.
LADWP will coordinate construction activities to minimize disruptions and maintain access to surrounding properties.
During construction:
- Temporary lane closures and parking restrictions may be necessary.
- Traffic control measures will be implemented as needed.
- Access to local streets and driveways will be maintained whenever possible.
- Residents and businesses will be notified of planned driveway restrictions.
- Construction equipment and crew vehicles may be present along the project route.
LADWP Contact Information
Project Engineering
Daniel Novoa
213-367-7709
Daniel.Novoa@ladwp.com
Community Affairs
Aldenae Williams
213-982-4066
Aldenae.Williams@ladwp.com