Per the Inyo County/Los Angeles Water Agreement, LADWP develops an annual operations plan consistent with the goals of the Water Agreement.

LADWP submits the draft plan covering the twelve-month period beginning April 1 to Inyo County by April 20 of every year. The County has 10 days (April 30) to review and comment on the draft plan then LADWP must meet with the technical group within 10 days (May 10) to resolve any concerns. LADWP then has 10 days (May 20) to revise and implement the final plan.