Program Background
LADWP delivers power to more than 4 million people across the City of Los Angeles. As the City continues to grow and electrify, substation capacity must increase to keep pace with the growing demand for electric power. Expanding and modernizing LADWP’s substation infrastructure will allow it to support growing community needs well into the future.
The Proposed Program aims to address this challenge by building new distributing substations in identified areas of need, expanding existing substations where feasible, and upgrading substation infrastructure. These improvements focus on relieving overloaded facilities, modernizing aging equipment, and meeting the City’s growing electricity needs to ensure reliable power delivery into the future.
Program Overview
LADWP proposes to modernize its electrical distribution system by constructing new distributing substations and improving existing distributing substations and receiving substations.
Each new distributing substation would be a fully enclosed facility designed to provide 32 to 90 MVA of capacity. Improvements at existing substations may include replacing existing equipment, adding new equipment, and general upgrades.
The Proposed Program would enhance system reliability, improve resiliency during extreme climate events, and support state and local clean energy goals. Expanding and modernizing LADWP’s substation infrastructure is essential to meet current needs and prepare for future demand.
Program Description
The Proposed Program consists of planned developments and conceptual improvements to the LADWP distribution system through the planning horizon year 2045. The Proposed Program includes the following components:
- New Development: construction of four new distributing stations to serve the Sun Valley, Silver Lake, Southeast Los Angeles, and Wilmington areas
- Expansion: expansion of existing substations
- Minor Improvements: minor improvements to existing substations
- Other Distribution System Improvements
Program Location
The Proposed Program would take place in the LADWP in-basin service area, which covers the City of Los Angeles. It identifies four areas of consideration for the new proposed distributing substations: the Sun Valley Study Area, Silver Lake Study Area, Southeast Study Area, and Wilmington Study Area. Each study area is defined by an approximate one mile-radius around a location that was identified by LADWP as an ideal operational location for a new distributing substation.
Any potential expansions of existing substations would occur within their current property boundaries or, if needed, adjacent acquired property. Minor improvements at existing substations would remain entirely within their existing sites. Other improvements to the distribution system would be located along current street rights of way or at locations where LADWP already has distribution infrastructure.
Environmental Review Process
Under the California Environmental Quality Act (CEQA), state and local government agencies are required to inform other agencies and members of the public about the potential environmental impacts of proposed activities, and to reduce or mitigate those impacts to the extent feasible. As the lead agency, LADWP will prepare a Program Environmental Impact Report (PEIR) to evaluate the potential environmental impacts of the Proposed Program. The PEIR will evaluate the broad, policy-level, and long-term environmental implications of the proposed Program, recognizing that subsequent site-specific actions may require additional CEQA review.
The Substation Program includes project-level analysis for well-defined components of the Program along with program-level analysis for future anticipated projects where the specific project details are not yet known. This programmatic approach will better inform agencies and interested parties about the overall environmental considerations of the Program.
A Notice of Preparation (NOP) of a Draft PEIR and Public Scoping Meeting has been prepared along with the Initial Study and can be accessed in Environmental Reports starting September 15, 2026.
Public Scoping Meetings
LADWP will hold virtual Public Scoping Meetings to share information regarding the Proposed Program and the environmental review process, and to solicit comments regarding the scope and content of the environmental analysis to be addressed in the PEIR. LADWP encourages all interested individuals and organizations to attend a meeting. The dates, times and details for the virtual Public Scoping Meetings are as follows:
Tuesday, September 29, 2026, at 6:00 p.m.
Thursday, October 1, 2026, at 11:00 a.m.
Public Review and Comments
LADWP invites comments on the scope and content of the environmental analysis to be included in the PEIR in connection with the Proposed Program. The public comment period for this NOP and review of the Initial Study will commence on September 15, 2026, and conclude on October 16, 2026.
Please send your comments or questions to:
By Mail:
Ms. Jazmin Martin
Los Angeles Department of Water and Power
Environmental Planning and Assessment
111 North Hope Street, Room 1044
Los Angeles, CA 90012
By Email:
SubstationProgram@ladwp.com
Online:
Comment Form
Remember to include your name and return address so that you can be added to the Program mailing list for future notifications. Your name, address, and comments become public information and may be released to interested parties if requested.
Please ensure that comments are postmarked or emailed on or before, October 16, 2026, the end of the public comment period.
Schedule
- Step 1: CEQA Program EIR Completion
- Step 2: Site Identification and Selection
- Step 3: CEQA Consistency Check, Tiering / Additional CEQA Review (if needed)
- Step 4: Project Design and Permitting
- Step 5: Project Construction
Contacts
Project Manager
Joseph Lee
(213) 851-0874
Joseph.Lee@ladwp.com
Community Affairs
Claudia Rodriguez
(213) 367-5218
Claudia.Rodriguez@ladwp.com